Brucejack Mine

THE PROJECT

Rokstad Power was awarded to construct approximately 5.4 miles of new single circuit Hoopes to Willis 69kV overhead electric transmission line between Buyer’s Hoopes substation and Willis substation in Chandler, AZ.  The scope included the modification and rebuild of a portion of the existing 69kV transmission line and associated 12kV distribution to create double circuit 69kV transmission line.

LOCATION: Chandler, AZ
CLIENT: Salt River Project
COMPLETION DATE: March 2019
CATEGORY: Transmission