Brucejack Mine
Owens

LOCATION: Arizona
CLIENT: Arizona Public Service
COMPLETION DATE: March 2018
CATEGORY: Transmission

Rokstad Power was awarded the construction of the Overhead line work consisting of:

◎    Building ~500' of double-circuit 69kV line from the new Owens Substation to the existing Preacher Canyon-Tonto 69kV line along Miller Road.
   Install 1-21kV switch.
   Replace 2 existing 69kV poles with 75’H6 poles.