LOCATION: Prescott, AZ
CLIENT: Arizona Public Service
COMPLETION DATE: May 2018
CATEGORY: Distribution

OH Scope: This was a 12kV rebuild, approximately 1 mile, including 31 pole replacements, OH conductor, and 7 associated transitions to UG.

UG Scope: Install approximately 1,450’ of Trench & Conduit (we subbed out to AZ Trench), pull 1,450’ of UG cable, splice, and terminate.