City of Lethbridge 138kV Live Line Rebuild

Project Description

Location: Lethbridge, Alberta
Details: 138kV Mono poles
Completion Date: June, 2014

Rokstad Power was engaged by the City of Lethbridge for the removal of 2 double circuit monopoles and the re-installation of 2 new double circuit 138kV monopoles using live line and barehand methods.

CHALLENGE
The work was conducted in extremely hot weather.

SOLUTION
Safety measures were implemented in order to protect work crews

RESULT
The client was very satisfied with our ability to complete the work successfully under the weather conditions.