Client Confidential, 230kV Line Construction

Project Description

Category
Transmission
Location: Saskatchewan
Details: 230kV, 18km
Completion Date: September, 2014

This project consisted of the construction of approximately 13km of new 230kv transmission line. The line was built using fiber reinforced polymer poles .

CHALLENGE
Construction was originally scheduled for winter months, but changes required that the  work be conducted in the spring and summer through a challenging wetland environment.

SOLUTION
Rokstad Power’s crews implemented a number of mitigation strategies in order to conduct the work efficiently and without impacts to the environment.

RESULT
Crews successfully completed this project with praise from the client and stakeholders. Rokstad Power was commended for environmental performance related to this project as well.